6. Construction Of Slurry Surfacing Systems

Inspection Points

Oversight of quality during construction is a shared responsibility between the agency and the contractor and is important in achieving a successful project.  Working together,...

Application Rates

Application rates may vary during the project due to changes in the existing pavement surface. The correct application rate of the treatment can have a...

Application

Thorough attention to detail is critical during the application process to ensure a successful final product. 1. Ambient Conditions for Application The basic prerequisites for successful...

Traffic Control

Traffic control plans and devices shall meet or exceed the minimum requirements of the “Manual on Uniform Traffic Control Devices” and should meet or exceed...

Notification

Notification about the project can yield positive results for the traveling public, the agency, and the contractor performing the work.  It is recommended that the...

Stockpile

The stockpile or staging area is where the contractor will store equipment and materials for the duration of the project. It should be in a...

Surface Preparation

There are two stages of surface preparation: early and final.  The early stage should be completed well in advance of project start-up.  The final stage...